Flexible Concrete Pavement Solutions
Stronger  •  Faster  •  Greener  •  Affordable

Where We Come From

An Australian invention, built for the toughest conditions on earth

  • Founded in Western Australia — born from the challenges of remote mining, industrial, and agricultural environments
  • Identified a gap — traditional pavements fail under heavy loads, extreme heat, and remote logistics
  • Millions invested in R&D to develop a completely new approach to pavement technology
  • Product is internationally patented — a protected invention across global markets
  • Proven in Australia's harshest conditions — Pilbara mine sites, feedlots, airports, heavy vehicle workshops
  • Now scaling nationally and internationally from three manufacturing facilities
Ancient Roman Appian Way cobblestone road
THE INSPIRATION

Roman cobblestone roads have lasted over 2,000 years. No other pavement system comes close. The reason? Interlocking modular pieces that flex and distribute load — instead of one rigid slab that cracks. That's the principle Rombus is built on.

What We Are

An Australian manufacturer solving a global problem

The Problem We Solve

Every operator knows these pain points

Cracked asphalt with potholes

Asphalt Fails

Wheel screwing, heat damage, constant maintenance. Short lifespan under heavy-duty traffic.

Cracked concrete pavement

Concrete is Costly

250mm+ slabs need formwork, steelwork, pump trucks. Costs spiral — especially in remote areas.

Mining haul road dust

Dust & Compliance

Unsealed surfaces create dust, drainage and access issues. Ongoing suppression costs and regulatory risk.

Heavy vehicles damaging industrial pavement

Downtime

Long construction schedules, lengthy curing, road closures. Every day of downtime costs money.

Rombus V1 Grid — The Original

Battle-tested on Tier 1 mining, civil and industrial projects

1000 × 1000
Tile Size (mm)
1 m² per tile
40 mm
Thickness
Minimal overlay profile
10,900 kg/m²
Compressive Strength
With concrete
1 m³ / 25 m²
Concrete Usage
~0.04 m³/m²
5.4 kg/m²
Recycled Plastic
5.6 kg per tile · 100% Aus. PP

Key Advantages

Distinctive geometric grid — proven structural lock pattern
Overlays directly onto failed slabs — no demolition
Used at BMA Blackwater & multiple heavy-vehicle workshops
In-situ repair — lift a section, fix subgrade, replace. Non-destructive
Granular fill compatible — road base, limestone, permeable aggregates
New install or overlay — onto 95% compacted subgrade, or directly over existing ground
Both V1 & V2: 40% faster install  ·  33% less on-site labour  ·  100% Australian recycled plastic

Rombus V2 Fusion ★ Recommended

The next generation — bigger tiles, simpler install, built for the heaviest loads

1165 × 1165
Tile Size (mm)
Larger sheet — fewer joins
48 mm
Thickness
Heavier-duty profile
10,900 kg/m²
Compressive Strength
With concrete
1 m³ / 21.7 m²
Concrete Usage
~0.046 m³/m²
5.6 kg/m²
Recycled Plastic
100% Australian PP

Key Advantages

Easier to install — simpler clipping, less training
No expansion joints — continuous monolithic finish
Engineered for the heaviest loads — thicker, stronger, simpler
Overlapping key joint — sheets interlock for a stronger panel-to-panel connection
One continuous shape — single repeating pattern, uniform load distribution
Palletised for container shipping — international deployment ready
Both V1 & V2: 40% faster install  ·  33% less on-site labour  ·  100% Australian recycled plastic

How It Works

From bare ground to finished pavement — faster than anything else

01
Prepare
Use existing ground. Minimal earthworks.
02
Lay Grid
Clip together on site. No skilled labour.
03
Pour
Concrete directly in. No pump trucks.
04
Screed
Level back to grid. 1 cube per 25 m².
05
Finish
Exposed aggregate or honed polish.
  • No formwork, no steelwork, no pump trucks, no control joints
  • 40% faster to install than traditional methods — 33% less labour on site

Install In Action

Quick, easy, minimal labour — vs a massive slab system, for similar or better results

LIVE INSTALL FOOTAGE
TRADITIONAL SLAB
  • Excavate & remove existing surface
  • Re-engineer sub-base
  • Formwork, rebar, large pour
  • Days of curing & downtime
ROMBUS
  • Lay tiles directly over existing surface
  • Clip together — no specialist trades
  • Pour shallow concrete (40–48 mm)
  • Operational in days, not weeks
40% FASTER  ·  33% LESS LABOUR

Built From What Would've Been Buried

Every Rombus tile diverts Australian plastic waste from landfill — not adds to it

Aerial view of plastic waste landfill
WHERE IT WAS HEADED
Australia sends ~2.5 million tonnes of plastic to landfill every year
EVEN ON A SMALL JOB
The BMA Blackwater workshop — just 1,200 m² — diverted
~6.5 tonnes
of 100% Australian recycled polypropylene from landfill
1,200 m² × 5.4 kg/m² = 6,480 kg recycled plastic locked into the workshop floor
>130,000 kg
CO² avoided on BMA — less concrete, no excavation
No demolition
Lays over existing surface — zero excavation, trucking or dump fees
Compounds at scale
Every m² installed = more waste plastic permanently out of the system

Case Study: BHP Mitsubishi Alliance — Part 1 of 2

BMA Blackwater, QLD — 1,200 m² heavy vehicle maintenance workshop

Severe cracking with pink survey markings on BMA Blackwater workshop slab
BEFORE — FAILED SLAB

Pink survey markings trace the network of cracks across the existing 200–350 mm fibre-reinforced concrete.

CAT 560 mining truck and crew preparing the workshop floor for Rombus install
DURING — LIVE WORKSHOP

A CAT 560 haul truck is parked metres from the work zone — the alternative was months of full demolition.

The Challenge

A 200–350 mm thick, 40 MPa fibre-reinforced slab on compacted sub-base had failed under heavy mining vehicle loads. Severe cracking, slab shifting, and groundwater pumping to the surface meant standard repair wasn't viable. Conventional remediation required removing 417 m³ of concrete, excavating, re-engineering the sub-base, and pouring a new slab — taking the workshop offline for months.

417 m³
Concrete to Remove
49 Days
Conventional Timeline
$1M+
Lost Productivity
High
CO₂ Footprint

Case Study: BHP Mitsubishi Alliance — Part 2 of 2

The Rombus solution — installed, finished, and operational in 10 days

Rombus grid laid directly over the failed slab
1. GRID LAID

1,200 m² of Rombus Grid laid directly over the failed slab — no demolition.

Finished smooth concrete floor after Rombus overlay
2. POURED

Just 45 m³ of concrete poured into and over the grid — a smooth, level finish.

Rombus grid pattern visible in cured surface
3. OPERATIONAL

Trafficable in 10 days — geometric grid signature visible in the cured wear surface.

~$780K
Saved
vs full removal & rebuild
>130,284 kg
CO₂ Avoided
Less concrete & earthworks
7,506 kg
Recycled Plastic
100% Australian polypropylene
39 Days
Faster
Operational in just 10 days

Our Facilities

Three manufacturing locations across Australia

Western Australia

Bibra Lake, Perth

Head office, R&D, and manufacturing. Serving WA's mining, industrial, and construction sectors.

South Australia

Elizabeth South, Adelaide

Manufacturing facility with Port of Adelaide access (~30 km). Export hub for international orders.

Queensland

Kunda Park, Sunshine Coast

Manufacturing facility serving Queensland and northern markets.

National & International

Australian made, globally available

Australia

Direct supply across all states and territories. Established relationships with Tier 1 miners, government, agriculture, and civil contractors. Growing dealer and distributor network. Three manufacturing facilities — WA, SA, QLD.

International

Internationally patented invention with global protection. Palletised shipping from Port of Adelaide. Two partnership pathways — distribution or commission agreement. Active interest from multiple international markets.

What Happens Next

Structured process — long-term partnerships, not transactions

Distribution

You provide

Minimum stock holding, local marketing, local presence, installation capability, grow your territory

We provide

Training, marketing materials, brochures, flyers, engineering updates, product support

Commission Agreement

You bring the purchase order to Rombus. We pay 3% commission on the PO. You do the work, you bring the business. We handle the sale — you earn.

Let's talk about your market.
08 6118 5229
Unit 2/4 Sobek Pass, Bibra Lake WA 6163
Stronger  •  Faster  •  Greener  •  Affordable